Plant design & configuration

Why this line is configured this way — in writing, before you buy anything

A configuration sheet is the most useful document in a crushing project, and the one most suppliers never produce. It shows every machine, why it is there, and what it has to do — so a performance discussion later is about settings, not opinions.

6 inputsWhat we need from you
3–4:1Reduction per cone stage
3–7 daysConfiguration turnaround
No costConfiguration and flow sheet

The six inputs

Line design is not creative work; it is arithmetic done in the right order. Give us six inputs and the flow sheet largely writes itself. Give us four and we can still start, but the quotation will carry assumptions — and assumptions are what turn into disputes.

Design inputs — what we need, and what each one decides
InputWhat we needWhat it decides
Material typeGranite, basalt, limestone, river stone, iron ore, C&D waste…Crusher family, wear strategy, whether a VSI is appropriate
Hardness / work indexCompressive strength, or a Bond work index figure, or an ore sampleCapacity calculation, motor power, liner selection
Feed gradationMaximum lump size and, if available, a sieve analysis of the feedPrimary feed opening, scalping arrangement, whether a gyratory is justified
Target capacityTonnes per hour and operating hours per dayMachine sizes across every stage, screen area
Required product sizesThe exact cuts you will sell, plus your market's specification limitsNumber of screens, deck count, mesh apertures, tertiary stage choice
Site conditionsPower supply and voltage, climate, altitude, water availability, footprint and transport constraintsDrive configuration, tropical package, wet or dry process, layout

These six also set the assumptions that go on the configuration sheet. If one is missing, we will state the assumption we used rather than quietly filling the gap.

How the reduction is split across stages

This is the part buyers most often get wrong when they specify a line themselves. Reduction ratio is cheap in the primary and expensive in the tertiary, so the design rule is: take as much reduction as early as the downstream machine can tolerate.

Typical reduction split
StageTypical reduction ratioDesign note
Primary (jaw or gyratory)3:1 to 6:1The cheapest reduction in the plant. Set as coarse as the secondary can accept — do not squeeze the primary to fix a downstream problem
Secondary (cone, open circuit)3:1 to 4:1Where the line's throughput is usually decided. Closed circuit with a pre-screen is normal practice
Tertiary (cone, closed circuit)3:1 to 4:1Fine product and product shape. Over-loaded tertiaries are the most common cause of a line missing its nameplate
Sand stage (VSI, closed circuit)Varies with rotor speedShape and gradation control; rotor speed is the tuning screw, set against your product test at commissioning
Why the screens matter more than the crushers. Screening is where plants lose their declared capacity, because an under-screened plant recirculates more than it should and the crushers end up doing work that screening should have done. When we size a line, we size the screen area first and choose the crushers to match — which is the opposite of how most quotations are built.

What the configuration sheet contains

A flow diagram showing every stream, every recirculation and every product take-off
An equipment list with model, quantity, motor power and the duty each machine performs
Discharge settings and expected product gradation at each stage
Screen area and deck arrangement, with apertures and the cuts each screen makes
Installed power total, starting-current considerations and the recommended supply arrangement
Utility requirements — water demand for wet process, compressed air if needed, dust suppression
Footprint and approximate layout envelope for your civil works and permitting
The assumptions the design rests on, stated explicitly so they can be checked

Turnaround is typically 3–7 days from receipt of complete input data. The configuration sheet is free and carries no obligation — a large share of our clients start here rather than with a price request, because it is the document that tells them whether their project is viable at all.

Configuration before quotation — the order matters

Quoting a price before the configuration is settled is how buyers end up comparing numbers that mean different things. A 300 t/h line is a different set of machines depending on whether the feed is 700 mm granite or 1,000 mm limestone, whether the market wants four product cuts or two, and whether the site has a rainy season. Two quotations for "300 t/h" can differ by 40% in equipment content and both be technically honest.

So we work in this order: inputs, configuration sheet, agreement on the configuration, then quotation. It takes a few days longer at the start and it removes almost all of the surprises later — including the expensive one where a client discovers at commissioning that the line does not produce the sizes their market actually buys.

Get a configuration sheet for your project

Send material type, hardness, feed size, target capacity, product sizes and site conditions. Flow sheet and equipment list back within 3–7 days, at no cost.