At 800 t/h the primary crusher deserves a serious comparison, secondary and tertiary crushing normally takes two machines, and the spare-parts bill has to be counted too.
Both primary routes are in range: the SJ.E jaw crusher is rated to 1,200 t/h, so one large unit can cover it; SK-series gyratory crushers start to be candidates at this capacity. The choice is not made on the capacity table but on feed size and the foundation budget. For secondary and tertiary crushing, two machines: the SK.D is rated 145–1,000 t/h under standard conditions, and after applying the crushability factor a single machine on hard rock lands in the upper-middle band — 800 t/h usually needs two to be safe.
There are real references at this level: an 800 t/h line in Ya'an, Sichuan runs two 1,800 single-cylinder cone crushers, and an 800 t/h granite line in Ningde, Fujian produces three sizes — 0–5, 5–16 and 16–30 mm — both in a 'one primary, multiple secondary and tertiary' layout. Count the spares too: the first stage is normally not backed up, while stages two and three carry one spare for every two or three machines and screens one for every three or four.
Shuangjin configures a line like this by fixing the primary crusher first, then setting the number of secondary and tertiary machines from the duty factor.
Applicable models: Shuangjin SK.Y series single-cylinder hydraulic cone crushers
Related product: SK.Y single-cylinder hydraulic cone crusher
Ask us directly. If it is a question we are asked often, it becomes the next article — and you get the answer either way.